3600 West Construction Project
Latest Update
3600 West And 2200 North Intersection Closure For Utility Work
| Phase | What's Happening | |
|---|---|---|
| 10/01/2026 | Expected Project Completion (October 2026) | Construction cleanup and final inspections mark the conclusion of the 3600 West infrastructure improvement. |
| 09/14/2026 | 2200 N Intersection Closure | Starting as early as Monday, Sept. 14, the intersection of 3600 W and 2200 N will be fully closed to all traffic for utility work involving deep trenches. For everyone's safety, the closure is expected to last up to three weeks. |
| 08/14/2026 | Paving & Striping | Paving takes place in two stages. The first phase covers the northern half of the route, scheduled for August 14 and 21. The second half is expected around mid-September and should take roughly one week. Crews will paint lines and install street signs right after paving. |
| 07/20/2026 | Road Widening & Concrete Work | As early as mid-July 2026, primary road widening reconstruction begins with curb and gutter work. Coordination with Plain City Elementary occurred on 7/30 to accommodate safe routes for children. |
| 07/07/2026 | Shift Utilities & Remove Asphalt | Work began July 7, 2026 with utility relocation efforts. Asphalt was removed along the entire route at the start of construction. Utility work continues. Local traffic only allowed. All detours will be posted. |
| No matching rows for the selected year. | ||
Job Site Photos
What does the work involve?
What are the work hours?
How is local access managed?
How are utility outages communicated?
Who can I contact for information?